Community Update

Keeping our neighbors informed as construction progresses. Questions? Email Community@thewellcg.com


FPL Power Interruptions

We are being advised by FPL that there will be several intermittent power outages over the course of the next two to three weeks. FPL will be performing outreach to all of the neighbors in advance of the power shutoffs so everyone can coordinate accordingly.

Latest Update

SEPTEMBER 18, 2026 · ACTIVE NOTICE

New Phase of Construction Underway

Construction is progressing well, with soil improvement and pile installation activities currently underway. Mass excavation has now begun and will continue over approximately the next 60 days. Foundation work is expected to start within the next 45 days.

Please note that Florida Power & Light will be performing intermittent power outages over a two-to-three week window as they transfer overhead power lines underground. This work is part of FPL's community storm-hardening improvement plan and will help improve grid reliability in the neighborhood during storm season.

Sidewalk and parking lane closures along Tigertail Avenue and Mary Street remain in effect for safety reasons as mandated by the City. Construction vehicles will continue to follow the designated route shown in the aerial image to the right, avoiding smaller internal neighborhood roads to minimize traffic impacts to our community.

If you have any questions, concerns, or feedback please use the "CONTACT US" button below or email us at Community@thewellcg.com, and we will do our best to get back to you as quickly as possible.

Contact Us

Construction Milestones

Key phases and progress to date

December 2025

Phase II — Soil Improvement Commences

In Progress
15% away from foundations

Earthwork & site preparation, fence relocation, FPL underground work

Fall 2026

Phase III — Vertical Construction Commences (28-month intended duration)

Upcoming Work

What to expect on site over the next 90 days

30-Day Lookahead

Next 30 Days

  • Mass Excavation
  • Piles
  • FPL
60-Day Lookahead

Next 60 Days

  • Mass Excavation
  • Foundations
90-Day Lookahead

Next 90 Days

  • Mass Excavation
  • Foundations

Community Information

How we're managing construction activity in the neighborhood

Construction phase crosswalk plan showing the shaded site outline and the pedestrian route around it, with existing crosswalk and sidewalk-ends points marked
Construction Phase
Final phase crosswalk plan showing the two new crosswalk locations, the existing crosswalk, and sidewalk-ends point
Final Phase

Have a question?

Don't see your question? Community@thewellcg.com.

This page was last updated on September 18, 2026.

FAQ — The WELL Coconut Grove

Frequently Asked Questions

Answers to the most common questions we've received from our Coconut Grove neighbors.

The Project

What is being built and why

The Well Coconut Grove is designed to be a curated space focused on health, connection, and well-being. Once complete, it will serve as a wellness destination for both residents and visitors, showcasing the natural spirit of the Grove.

Soil Improvement commenced in December 2025, with vertical construction expected to begin by Fall 2026. We appreciate the community's patience and support as we work to bring this project to life.

The barrier wall has been installed in accordance with City safety guidelines to protect the public during active construction. The art fence is a more aesthetic alternative to traditional chain-link fencing. We're committed to minimizing disruption as much as possible.

Construction Impacts

Traffic, noise, dust, and day-to-day disruptions

We are working closely with the City to manage traffic flow and minimize disruptions. Temporary lane closures may be necessary at times, but trained flagmen will be on-site. We greatly appreciate your patience and understanding during this time.

Regular street cleanings help minimize dust and debris, and all work is conducted within permitted hours to limit noise disruptions. Maintaining a clean and safe environment remains our priority throughout the project.

We are coordinating with the City and County on walkability during construction. We installed a temporary mid-block crosswalk on Mary Street to help maintain safe and accessible routes for families, students, and neighbors. Any new crosswalks are subject to Miami-Dade County's approval.

For safety purposes, the City has mandated that sidewalks and parking lanes abutting the property remain closed during construction. We installed a temporary mid-block crosswalk on Mary Street during the demolition phase to support walkability.

The perimeter barricade, fence, and number of gates are all compliant with the approved MOT plan. Multiple gates improve the maneuverability of delivery vehicles, avoiding the queuing that would result from a single entry and exit point.

Have a question?

Don't see your question? Community@thewellcg.com.

This page was last updated on April 7, 2026