Community Update
Keeping our neighbors informed as construction progresses. Questions? Email Community@thewellcg.com
We are being advised by FPL that there will be several intermittent power outages over the course of the next two to three weeks. FPL will be performing outreach to all of the neighbors in advance of the power shutoffs so everyone can coordinate accordingly.
Latest Update
New Phase of Construction Underway
Construction is progressing well, with soil improvement and pile installation activities currently underway. Mass excavation has now begun and will continue over approximately the next 60 days. Foundation work is expected to start within the next 45 days.
Please note that Florida Power & Light will be performing intermittent power outages over a two-to-three week window as they transfer overhead power lines underground. This work is part of FPL's community storm-hardening improvement plan and will help improve grid reliability in the neighborhood during storm season.
Sidewalk and parking lane closures along Tigertail Avenue and Mary Street remain in effect for safety reasons as mandated by the City. Construction vehicles will continue to follow the designated route shown in the aerial image to the right, avoiding smaller internal neighborhood roads to minimize traffic impacts to our community.
If you have any questions, concerns, or feedback please use the "CONTACT US" button below or email us at Community@thewellcg.com, and we will do our best to get back to you as quickly as possible.
Contact UsConstruction Milestones
Key phases and progress to date
Phase II — Soil Improvement Commences
Earthwork & site preparation, fence relocation, FPL underground work
Phase III — Vertical Construction Commences (28-month intended duration)
Upcoming Work
What to expect on site over the next 90 days
Next 30 Days
- Mass Excavation
- Piles
- FPL
Next 60 Days
- Mass Excavation
- Foundations
Next 90 Days
- Mass Excavation
- Foundations
Community Information
How we're managing construction activity in the neighborhood
The safety of pedestrians remains a priority. We installed a temporary crosswalk mid-block on Mary Street to create a contiguous pedestrian path since the current sidewalk on the west side of Mary Street does not continue north to Day Avenue. Any proposed new temporary and permanent crosswalks are subject to Miami-Dade County's approval.
Regular street cleanings help minimize construction dust and debris. Storm drains are actively maintained as part of our Stormwater Pollution Prevention Plan (SWPPP). Street cleaning and storm drainage maintenance will be ongoing during all construction activity and will occur daily.
The number of gates installed is compliant with the approved Maintenance of Traffic (MOT) plan. This layout improves the maneuverability of delivery vehicles, avoiding the stalling that would occur with a single entry and exit point.
Beginning January 5th, sidewalks and parking spaces abutting the project on Tigertail Avenue and Mary Street will be closed for safety reasons as mandated by the City. We will continue coordinating with the City and Miami-Dade County to maintain safe and accessible pathways, and will notify the community of any lane closures.
For safety purposes during construction, the City has mandated that sidewalks and parking lanes abutting the property on Tigertail Avenue and Mary Street remain closed. We installed a temporary mid-block crosswalk on Mary Street during the demolition phase. Any proposed new temporary and permanent crosswalks are subject to Miami-Dade County's approval.
We will continue to monitor traffic patterns and communicate any temporary lane closures. Emergency vehicle access and overall traffic flow will remain steady. Tigertail Avenue is a shared-use vehicle and bike path lane — vehicular lanes will remain open so cyclists can continue to circulate as customary.
We're committed to keeping our neighbors informed as construction progresses through this website, email updates, and Instagram. If you have questions, email us at Community@thewellcg.com.
Have a question?
Don't see your question? Community@thewellcg.com.
This page was last updated on September 18, 2026.
Frequently Asked Questions
Answers to the most common questions we've received from our Coconut Grove neighbors.
The Project
What is being built and why
The Well Coconut Grove is designed to be a curated space focused on health, connection, and well-being. Once complete, it will serve as a wellness destination for both residents and visitors, showcasing the natural spirit of the Grove.
Soil Improvement commenced in December 2025, with vertical construction expected to begin by Fall 2026. We appreciate the community's patience and support as we work to bring this project to life.
The barrier wall has been installed in accordance with City safety guidelines to protect the public during active construction. The art fence is a more aesthetic alternative to traditional chain-link fencing. We're committed to minimizing disruption as much as possible.
Construction Impacts
Traffic, noise, dust, and day-to-day disruptions
We are working closely with the City to manage traffic flow and minimize disruptions. Temporary lane closures may be necessary at times, but trained flagmen will be on-site. We greatly appreciate your patience and understanding during this time.
Regular street cleanings help minimize dust and debris, and all work is conducted within permitted hours to limit noise disruptions. Maintaining a clean and safe environment remains our priority throughout the project.
We are coordinating with the City and County on walkability during construction. We installed a temporary mid-block crosswalk on Mary Street to help maintain safe and accessible routes for families, students, and neighbors. Any new crosswalks are subject to Miami-Dade County's approval.
For safety purposes, the City has mandated that sidewalks and parking lanes abutting the property remain closed during construction. We installed a temporary mid-block crosswalk on Mary Street during the demolition phase to support walkability.
The perimeter barricade, fence, and number of gates are all compliant with the approved MOT plan. Multiple gates improve the maneuverability of delivery vehicles, avoiding the queuing that would result from a single entry and exit point.
Have a question?
Don't see your question? Community@thewellcg.com.
This page was last updated on April 7, 2026